Anonymous project · Commercial office building

Riser containment and Cat6A backbone through a multi-floor building

New basket containment, segregated Cat6A backbone runs and fire-stopped cable transits through compartment walls.

Riser containment and Cat6A backbone through a multi-floor building
Service
Structured Cabling
Sector
Commercial office building
Location
London

The brief

A building riser needed new data containment and backbone cabling installed to serve floor distributors — without compromising the fire compartmentation between floors and plant areas.

What we delivered

  • Wire basket tray and unistrut support steelwork through the riser route
  • LSZH Cat6A backbone looms, banded at regular intervals, maintained bend radius through every change of direction
  • Physical segregation from power circuits sharing the route, with earth bonding continuity across containment sections
  • Proprietary multi-cable transit frames at compartment penetrations, re-sealed and inspected after cable installation — the barrier is only as good as its reinstatement

The detail that matters

Fire-stopping is the part of a cabling job nobody sees and every building control officer checks. We treat transit reinstatement as part of the cabling scope, not someone else’s problem.

Handover

Route photographs, transit register for the fire-stopping record, and test results for the installed links.

Client identity withheld. Photos are from field work delivered by GLOBALPROCABLING engineers; site and company names are anonymised by design.

Tell us about your project.

Direct quote or contractor overflow — reply within one working day.

CallGet Quote